Commercial Strip Out Regulations UK: CDM, Asbestos and Waste

Short answer

Commercial strip outs in the UK must comply with the Construction (Design and Management) Regulations 2015, which require planning and competent contractors. A refurbishment and demolition asbestos survey is needed before the building fabric is disturbed. Refrigerant must be recovered by F-gas certified technicians, WEEE must go to suitable treatment, gas work needs a Gas Safe registered engineer, and all waste is subject to the duty of care.

Commercial Strip Out Regulations UK: CDM, Asbestos and Waste

CDM 2015

The Construction (Design and Management) Regulations 2015 apply to strip out work, because it counts as construction work. The client, usually the tenant or landlord commissioning the strip out, has duties to make suitable arrangements for managing the project, provide relevant information such as the asbestos register, and appoint competent contractors.

Where more than one contractor is involved, the client must appoint a principal designer and a principal contractor. A construction phase plan, proportionate to the risks, must be in place before work starts. Larger projects must be notified to the HSE if they last more than 30 working days with more than 20 workers on site at any one time, or exceed 500 person days.

For a small shop strip out by one contractor, the paperwork is light. For a multi-floor office, it is more involved.

RuleWhat it means for a strip out
CDM 2015Planning, competent contractors, construction phase plan
Control of Asbestos Regulations 2012R&D survey before disturbing the fabric
F-gas rulesRefrigerant recovered by certified technicians
WEEE Regulations 2013Electrical equipment to suitable treatment
Gas Safety (Installation and Use) Regulations 1998Gas work by Gas Safe registered engineers
Environmental Protection Act 1990, s.34Duty of care for all waste

Asbestos

Many commercial buildings constructed or refurbished before 2000 contain asbestos, in ceiling tiles, floor tiles, textured coatings, pipe lagging, boards and other materials. The Control of Asbestos Regulations 2012 require that, before any refurbishment or demolition work disturbs the building fabric, a refurbishment and demolition survey is carried out in the areas affected.

The building's existing asbestos register is a management survey and is not enough on its own for a strip out. The R&D survey is intrusive and identifies materials that the work will disturb. Any asbestos found must be removed by suitably licensed or trained contractors before the strip out proceeds in that area.

Allow time for this in the programme. Surveys and any removal can take several weeks.

Refrigerant, WEEE and lighting

Air conditioning units, cold rooms, chillers and refrigerated display cases contain fluorinated gases. Under the F-gas rules, refrigerant must be recovered by a technician holding the appropriate F-gas certification before the equipment is disconnected or removed. Venting refrigerant is illegal.

Electrical and electronic equipment, including IT kit, lighting, kitchen appliances and control panels, falls under the WEEE Regulations 2013 and must go to a suitable treatment route. Fluorescent tubes and some other lamps are hazardous waste because they contain mercury, so they must be kept intact, segregated and moved with the correct consignment paperwork in England and Wales.

Data-bearing IT equipment should be wiped or destroyed by a specialist before disposal.

  • Recover refrigerant before removing air conditioning or cold rooms
  • Keep fluorescent tubes intact and segregated
  • Separate IT, lighting and appliances as WEEE
  • Arrange certified data destruction for drives and servers
  • Keep certificates and consignment notes

Isolating gas, electricity and water

Services must be safely isolated before removal. Gas appliances and pipework in restaurant kitchens and boiler rooms must be disconnected and capped by a Gas Safe registered engineer, as required by the Gas Safety (Installation and Use) Regulations 1998. Electrical circuits should be isolated and made safe by a competent electrician, with the work certified as appropriate.

Water supplies to kitchens, toilets and tea points should be isolated and capped to prevent leaks, which can cause serious damage to floors below. Agree with the landlord which services are capped at what point, particularly in multi-let buildings where shared risers are involved.

Waste duty of care

Under section 34 of the Environmental Protection Act 1990, whoever produces the waste has a duty of care. On a strip out that is usually the contractor, but the client should still check that waste goes to registered carriers and permitted sites. Waste transfer notes must be kept for at least two years, and hazardous waste consignment notes for three years in England and Wales.

Segregating waste on site, into metal, timber, plasterboard, inert material, WEEE and general mixed waste, helps meet these duties and usually reduces cost. Ask your contractor to provide a summary of waste streams and the paperwork at the end of the job.

Working safely in occupied buildings

Many strip outs take place in buildings where other tenants are still working. That means controlling noise, dust and vibration, keeping fire escape routes clear, protecting lifts and common parts, and agreeing working hours with the landlord or managing agent. Fire alarm and sprinkler systems must stay effective or be managed under a proper permit system.

The construction phase plan should cover all of this. Good communication with the building manager avoids most problems.

A pre-start checklist

Before any strip out begins, a short checklist helps make sure the legal and practical requirements are in place. It is a useful tool for clients as well as contractors, because it shows the questions to ask and the documents to expect. On smaller jobs most of these points can be covered in a single meeting.

Keep a copy of the completed checklist with the project file. It forms part of the evidence that the work was properly planned under CDM 2015.

  • Scope and target condition agreed in writing
  • R&D asbestos survey completed for affected areas
  • Construction phase plan in place
  • Landlord consents, working hours and lift bookings confirmed
  • Gas, electrical and water isolation arranged with the right trades
  • F-gas recovery booked for refrigeration and air conditioning
  • Waste carriers checked and waste routes agreed

Questions people also ask

Does CDM 2015 apply to a strip out?

Yes. Strip out work is construction work, so CDM 2015 applies. The client must make suitable arrangements and appoint competent contractors, and a construction phase plan is needed. Where more than one contractor is involved, a principal designer and principal contractor must be appointed.

Do I need an asbestos survey before a strip out?

Yes, if the work will disturb the building fabric. The Control of Asbestos Regulations 2012 require a refurbishment and demolition survey of the affected areas before work starts. An existing management survey is not enough on its own.

Who can remove air conditioning units?

The refrigerant must first be recovered by a technician holding the appropriate F-gas certification. Once recovered, the units can be disconnected and removed by the strip out team and sent for suitable WEEE treatment. Venting refrigerant to the atmosphere is illegal.

Written and checked by the Commercial Strip Out team. Read our editorial policy.